Nepal Government Rate Analysis Norms
Download authorized rate analysis norms and standard technical specifications from DUDBC, Department of Roads (DoR), DoWRI, and DWSSM for preparation of construction estimates, tenders, and municipal approvals.
Need Current Year District Rates?
Combine these norms with approved 77 District Jilla Dar Rates to calculate official unit costs per item.
DUDBC Standard Rate Analysis Norms for Building Works
Standard labor, material coefficients, and machinery outputs for earthwork, masonry, RCC works, plastering, painting, and roofing per DUDBC guidelines.
Department of Roads (DoR) Standard Norms for Road & Bridge Works
Complete technical coefficients for sub-base, base course, asphalt/premix carpeting, heavy earth-moving equipment outputs, and bridge substructure/superstructure.
DUDBC Sanitary, Plumbing & Electrical Rate Analysis Norms
Standard analysis norms for internal and external water supply lines, sanitary fittings, CPVC/PPR pipes, electrical wiring, distribution boards, and fixtures.
Automated Rate Analysis Excel Template (DUDBC / DoR Format)
Pre-formatted Excel spreadsheet with automated formulas. Enter 77 district material/labor rates to automatically compute unit rates with 15% contractor profit and VAT.
Department of Water Resources & Irrigation (DoWRI) Norms
Norms for canal excavation, embankment compaction, gabion crate wire weaving, boulder packing, and river training structures.
DWSSM Water Supply & Sewerage Construction Norms
Norms for trench excavation, pipeline jointing (HDPE/GI/DI), RCC reservoirs (OHT/Cisterns), and deep tube well drilling operations.
⚙️ Standard Government Rate Analysis Breakdown in Nepal
Material Cost (per norm) + Skilled/Unskilled Labor Wages + Plant, Equipment, and Fuel hiring charges.
15% Overhead and Profit (OHP) is officially added directly to the total sum of Material + Labor + Equipment costs.
13% Value Added Tax (VAT) is calculated at the Bill of Quantities (BoQ) summary level per Nepali procurement norms.